Appearing for PMP Certificate Exam? Get the latest updates about PMP Exam changes here. This is part-5 in series of PMP Practice Exam Questions related to Project Quality Management for PMP Certification covering Project Quality Management related questions. In the previous part, we have discussed about PMP Exam questions related to Project Cost Management.
- PMP Practice Exam Questions – Project Integration Management (Part 1)
- PMP Practice Exam Questions – Project Scope Management (Part 2)
- PMP Practice Exam Questions – Project Schedule Management (Part 3)
- PMP Practice Exam Questions – Project Cost Management (Part 4)
- PMP Practice Exam Questions – Project Quality Management (Part 5)
- PMP Practice Exam Questions – Project Resource Management (Part 6)
- PMP Practice Exam Questions – Project Communication Management (Part 7)
- PMP Practice Exam Questions – Project Risk Management (Part 8)
- PMP Practice Exam Questions – Project Procurement Management (Part 9)
- PMP Practice Exam Questions – Project Stakeholder Management (Part 10)
PMP Practice Exam Questions List – Project Quality Management:
Here is the list of PMP Practice Exam Questions related to Project Quality Management.
Question 1:
Which of the following tools and techniques is useful to process work performance data to identify sources of project defects during the Control Quality Process?
- A) Data analysis
- B) Salience model
- C) Schedule model
- D) Communication model
Correct Answer: A
Check out the solution:
The question is asking for a tool and technique used during the Control Quality process. Data Analysis is a tool and technique of the Control Quality process used to identify source of defects.
Question 2:
An effective quality audit should be:
- A) Structured and independent
- B) Informal and independent
- C) Informal and internal
- D) Structured and internal
Correct Answer: A
Check out the solution:
To provide the best results, a quality audit should be a structured process performed by an independent entity.
Question 3:
A control chart should always contain:
- A) Upper and lower warning limits
- B) The moving average
- C) Upper and lower control limits
- D) Upper and lower specification limits
Correct Answer: C
Check out the solution:
Upper and lower control limits allow the control chart to serve its purpose of indicating when a process is in or out of control.

- Joseph Philips via Udemy
- 168,299+ students enrolled!
- ★★★★★ (57,916 Ratings)

- Andrew Ramdayal via Udemy
- 13,237+ already enrolled!
- ★★★★★ (4,429 Ratings)

- Chris Croft via Udemy
- 15,940+ already enrolled!
- ★★★★★ (5,111 ratings)
Question 4:
The Plan-Do-Check-Act (PDCA) cycle as the basis for quality improvement is usually attributed to:
- A) Deming
- B) Crosby
- C) Juran
- D) Pareto
Correct Answer: A
Check out the solution:
The plan-do-check-act (PDCA) cycle was defined by Shewhart and later modified by Deming.
Question 5:
Which of the following Manage Quality techniques examines problems, constraints, and non-value-added activities that occur during project work?
- A) Sensitivity Analysis
- B) Expected monetary value analysis
- C) Earned Value Analysis
- D) Process Analysis
Correct Answer: D
Check out the solution:
Process Analysis examines problems, constraints, and non-value- added activities that occur during project work.
You can find more PMP Practice Exam Questions – Project Quality Management for the PMP Certification here.